Prioritise a constrained backlog

Make trade-offs explicit across customer value, risk and deadlines.

Intermediate20 minFictional scenario

The brief

A Scrum team can take two of three items: a regulatory consent change due next month, a recurring onboarding error, or a cosmetic dashboard refresh.

What you know

The error affects 18% of applicants. The dashboard request has no measured customer problem. The consent change has a fixed deadline.

Your deliverables

  • Ranked backlog
  • Rationale and assumptions
  • One piece of evidence that could change the ranking

Your working notes

Write a draft before opening the comparison. Notes stay in this browser.

Compare with a reference approach

Prioritise the fixed compliance commitment and investigate the high-impact onboarding error. Defer the cosmetic change pending evidence. Make dependencies and uncertainty visible; revisit after discovery.